Your all-in-one solution

Your trusted partner for HVAC design, installation, maintenance, and repair.

Committed to sustainability

Sustainability is at the heart of everything we do.

24/7/365 contracted call outs

Rapid response whenever you need us most.

Honesty and integrity

Building trust through transparent practices.

Haverhill

Client

xxxxxxxxx

Duration

xxxxxxxxxx

Value

xxxxxxxxxxx

Haverhill

Overview

This project involves the complete overhaul of the sanitary and water supply systems in a building, encompassing both new and existing areas. The primary focus is on the installation of new above-ground drainage systems, domestic water supply lines, and sanitary fixtures in the kitchens, cleaners’ areas, and toilet blocks.

Key Deliverables

Drainage System

  • Installation of new above-ground drainage pipes to serve the kitchens and cleaners’ area. 
  • Connection of the new drainage system to the existing infrastructure.
  • Installation of a commercial Saniflo pump. 

Water Supply

  • Extension of the existing boosted water supply from the ground floor unit to new outlets in the kitchens and cleaners’ area.
  • Connection of sinks to the water supply lines.
  • Insulation of all pipework.
  • Supply and installation of four under-sink unvented water heaters with safety kits. 

Sanitary Fixtures & Fittings 

  • Supply and installation of an Ideal Standard Cleaners sink with a bucket grid and taps.
  • Extension of hot and cold water supplies to the new sinks in the male toilets.
  • Installation of a 15mm isolated cold water supply adjacent future drainage connection.

Toilet Blocks

  • Isolation, disconnection, and removal of existing sanitary ware and hot water heaters in preparation for building alterations.
  • Modification of pipework to accommodate new layouts.
  • Installation of a Cistermiser sensorzone water controller with PIR to conserve water in toilet blocks.
  • Installation of flow restrictors at all outlets.
  • Supply and installation of sanitary fixtures, including toilet pans, concealed cisterns, flush plates, ambulant toilets, grab rails, TMVs, urinals, urinal cisterns, spreaders, urinal controls, and basin mixers.
  • Installation of a 30L Heatrae Multipoint Eco vertical unvented water heater in each toilet block.
  • Supply and installation of a 150L direct hot water cylinder with a Grundfos HW pump and thermal balancing valves.

Summary

This project will provide a comprehensive upgrade to the building’s sanitary and water supply systems, ensuring efficient operation, water conservation, and compliance with building regulations.  

Read More Contracting Case Studies: