Client
Mixbrow
Duration
10 Months
Value
£190,000
Haverhill
Overview
This project involves the complete overhaul of the sanitary and water supply systems in a building, encompassing both new and existing areas. The primary focus is on the installation of new above-ground drainage systems, domestic water supply lines, and sanitary fixtures in the kitchens, cleaners’ areas, and toilet blocks.
Key Deliverables
Drainage System
- Installation of new above-ground drainage pipes to serve the kitchens and cleaners’ area.
- Connection of the new drainage system to the existing infrastructure.
- Installation of a commercial Saniflo pump.
Water Supply
- Extension of the existing boosted water supply from the ground floor unit to new outlets in the kitchens and cleaners’ area.
- Connection of sinks to the water supply lines.
- Insulation of all pipework.
- Supply and installation of four under-sink unvented water heaters with safety kits.
Sanitary Fixtures & Fittings
- Supply and installation of an Ideal Standard Cleaners sink with a bucket grid and taps.
- Extension of hot and cold water supplies to the new sinks in the male toilets.
- Installation of a 15mm isolated cold water supply adjacent future drainage connection.
Toilet Blocks
- Isolation, disconnection, and removal of existing sanitary ware and hot water heaters in preparation for building alterations.
- Modification of pipework to accommodate new layouts.
- Installation of a Cistermiser sensorzone water controller with PIR to conserve water in toilet blocks.
- Installation of flow restrictors at all outlets.
- Supply and installation of sanitary fixtures, including toilet pans, concealed cisterns, flush plates, ambulant toilets, grab rails, TMVs, urinals, urinal cisterns, spreaders, urinal controls, and basin mixers.
- Installation of a 30L Heatrae Multipoint Eco vertical unvented water heater in each toilet block.
- Supply and installation of a 150L direct hot water cylinder with a Grundfos HW pump and thermal balancing valves.
Summary
This project will provide a comprehensive upgrade to the building’s sanitary and water supply systems, ensuring efficient operation, water conservation, and compliance with building regulations.